Netting Facility At Peddie Ditch

The Peddie Ditch CSO solids/floatables control floating structure is in disrepair, and is being replaced with a netting facility. Currently the project is in design (Arcadis US, Inc.) and permitting stage and expected to begin construction in fall 2017 and continue through summer of 2018.

Contact information

Breana Whittaker, (973) 256-4965

$205,437.00

$486,580.00
APPROXIMATELY $4,000,000.00

NJEIT low interest loan #S340815-26

Consultant:

Arcadis US, Inc.

Contract:

Contract 07-WS2016: